Until this month, Estero drivers heading north on it ran out of road just past Alico Road. Since November 3, the road crosses the Fiddlesticks Canal and continues to Daniels Parkway. The road you already take to Coconut Road or Corkscrew Road now leads to a Publix plaza, the main road to Southwest Florida International Airport, and the Red Sox spring training ballpark.

Lee County opened the extension the day after a November 2 ribbon cutting. The road opened nearly 18 months early. The original schedule called for mid-2028. In the county's words, the extension "completes the Three Oaks Parkway corridor," a major north-south road that runs from Daniels Parkway south through the Village of Estero, the City of Bonita Springs and into Collier County.

The Road Through Estero Now Runs North to Daniels

For most of the village, Three Oaks Parkway is a road you cross or drive a short stretch of. In Estero it meets Coconut Road, Williams Road, Estero Parkway and Corkscrew Road. Until this fall, its northern end stopped short of the Fort Myers places Estero residents visit most often.

The new section changes that. Phase 1 runs north of Alico Road from the Fiddlesticks Canal to about Indian Paint Lane. Phase 2 continues from there to Daniels Parkway, ending where Fiddlesticks Boulevard and Palomino Lane meet Daniels. Lee County calls the corridor "critical north/south relief to Interstate 75." WINK News reported that officials expect the extension to take local traffic off I-75 and ease congestion.

For someone driving from Estero, that means the trip north to Daniels can now stay on local roads the whole way.

First Stop: The Roundabout at Fiddlesticks Boulevard

Just before Daniels Parkway, the extension has a new roundabout at Fiddlesticks Boulevard and Old Fiddlesticks Boulevard. The county says it was built to give access to the Publix shopping center at that corner. The center is The Shoppes at Fiddlesticks, at 13650 Three Oaks Parkway. Its tenants include The UPS Store in Suite 202.

That address puts the plaza at the north end of a road Estero residents already know. If you already make a weekly trip up to the Daniels area, you can now turn into the plaza from Three Oaks Parkway without leaving the road.

Turning East on Daniels Parkway

At Daniels Parkway, two of the region's most-visited destinations are a few turns east.

Southwest Florida International Airport. The Lee County Port Authority's directions to its RSWRemote parking lot start on Daniels Parkway at I-75 Exit 131. From there you turn south onto Chamberlin Parkway, enter the Skyplex area and turn onto Regional Lane. The terminal itself is at 11000 Terminal Access Road.

JetBlue Park at Fenway South. The Red Sox spring training ballpark is at 11500 Fenway South Drive. The team's own directions send drivers east on Daniels Parkway from Exit 131, straight through the Treeline Avenue intersection, then 1.6 miles to the ballpark on the left. The Red Sox 2027 spring schedule lists Friday, February 19, against Northeastern as the first home game. Game times and ticket details are still marked "TBD" and "to be announced."

Here is what sits at the north end of the corridor:

Destination Address Route from the end of Three Oaks Parkway
The Shoppes at Fiddlesticks 13650 Three Oaks Parkway Roundabout at Fiddlesticks Boulevard and Old Fiddlesticks Boulevard
RSWRemote parking Regional Lane, Skyplex area Daniels Parkway at Exit 131, then south on Chamberlin Parkway
JetBlue Park at Fenway South 11500 Fenway South Drive East on Daniels past Exit 131 and Treeline Avenue, then 1.6 miles

Built With Room for Bikes and Walkers

The extension has two 11-foot lanes in each direction and a median 14 to 18 feet wide. Each side has a 5-foot bike lane. On the first segment north of Alico Road, the project website lists an 8-foot sidewalk on the west side and a 6-foot sidewalk on the east side. The second segment, toward Daniels, has 6-foot sidewalks on both sides.

The county seemed to expect people to arrive on foot and by bike. Its ribbon cutting announcement invited neighbors from nearby residential areas to walk or bicycle to the event.

What Crews Are Still Finishing

The road is open, but the project isn't complete. Lee County says contractors will stay on site to finish punch-list items, and final completion is scheduled for early 2027. Here is what's left on and near the route:

  1. The Daniels Parkway intersection. Work at Three Oaks Parkway and Palomino Lane is finished once the lanes are restriped.
  2. The eight-lane section of Daniels. Daniels has been widened to eight lanes from Danport Boulevard to Appaloosa Lane and Powers Court. All eight lanes open after final paving and striping. In the county's Roadwatch for October 29 to November 4, Daniels had three lanes open in each direction, with the outside lanes still closed for construction.
  3. The I-75 interchange at Daniels. The same Roadwatch listed ongoing reconstruction of the I-75 interchange at Daniels Parkway, with possible nighttime lane closures on Daniels. That matters on early-morning airport runs and late-night pickups.
  4. Corkscrew Road Phase 2. If you reach Three Oaks from the eastern side of Estero, Corkscrew Road is still under construction. The Phase 2 widening, from Bella Terra Boulevard to just east of Alico Road, is now expected to be finished in late spring 2027. The Roadwatch notes intermittent daytime flagging on Corkscrew and Alico while crews work up to the shoulders.

Lane patterns change as paving moves along, so the most reliable source is Lee County's weekly Roadwatch update. A new one posts every Thursday. The Three Oaks Parkway Extension project site has a recording of the ribbon cutting and a sign-up form for project updates.

Your Route North Through the Season

Over the next few months, the corridor will see Thanksgiving airport runs, holiday shopping trips and then spring training. The first game at JetBlue Park is February 19, and the county expects to finish the project in early 2027. If paving and striping on Daniels are done by then, the trip from the Estero end of Three Oaks Parkway to the ballpark should be on finished roads all the way. Until then, a quick look at Thursday's Roadwatch will tell you which lanes are open.

How quickly you can reach Daniels Parkway, the airport and the ballpark is something we talk through with Estero clients when they compare communities near Corkscrew Road, Estero Parkway or Coconut Road. If you'd like to know what this route means for your part of the village, The Westerfield Group is glad to talk it over. Let's Connect.